Project: Church Refurbishment
Address: Woodlands Road, Glasgow
Client: Free Presbyterian Church of Scotland
Contract Administrator: NBM Cost Consultants
Project Value: £195,000.00
Duration: 8 Weeks
WMR were appointed as principal contractor in the refurbishment of this B Listed church in Glasgow’s West End. In conjunction with Historic Scotland, the local authority and Contract Administrator works were overtaken in a short 8-week period and included:
• Restoration of existing floors and pews
• Lath & plaster repairs
• Dry rot repairs
• Scaffolding
• Decoration
• Overhaul of M&E systems