Project: Escape of Water Refurbishment
Address: Darnley, Glasgow
Client: Davies Group PLC
Contract Administrator: Anderson Building Consultancy
Value: £105,000.00
Duration: 7 Weeks
WMR successful tendered and were appointed as Principal Contractor to the reinstatement of this water damaged residential property in Glasgow. The project involved a full internal refurbishment and fit out and were completed in a short 7 week duration.
Works included but were not limited to:
• New electrical system
• New heating system
• New external wall insulation and linings
• Floor structure repairs and replacement
• New internal partitions and doors
• New ceiling structure
• Bathroom replacement
• Kitchen replacement
• Plastering
• Decoration
• Tiling
• Floor covering replacement