Project: Escape of Water – Insurance Reinstatement
Address: Gartcraig Road, Glasgow
Client: Private Client
Contract Administrator: Davies Group PLC
Project Value: £115,000.00
Duration: 8 weeks
WMR were approached directly by this client to handle their insurance claim. The client opted to pass management of the claim over to WMR. WMR produced a Schedule of Works, which was then reviewed and agreed upon with surveyors from the Davies Group.
The works included:
• Full strip out
• Asbestos Removals
• Drying
• Propping & structural repair
• New insulation
• New wall, floor & ceiling linings
• Decoration
• New Kitchen
• New bathroom
• All new M&E services